I’ve got a load of dates for certain jobs to commence (column D) and a I need a corresponding set of dates (column E) when I need the work completing by, standard turn around being 30 working days (i.e. 6 weeks excluding weekend days). So D2+42 sorts that out.
The problem is that I need to exclude other days where work won’t happen (bank holidays and some other days). I’ve got a list of those dates in Excel.
So say for example job 1 starts on Monday 1/8/16 it should be completed by Tuesday 13 September. Standard 30 working days plus the bank holiday Monday in August. How can I get Excel to work this shit out for me?
Obviously I could do D2+42, copy down and manually adjust where bank holiday/non-work days appear in the 6 weeks, but that’d be a right ball ache as there’s loads of jobs I need to log.